Give to me guidelines in calibration inspection what i am done in calibration cycle below steps
IE01 - I created equipments
qs21 - I created calibration specifications in different equipments
IA01 - I created equipment task list
Ip41 - I created Maintenance plan in that plan maintenance plan cycle i put 6 months and Mainpl scheduling parameters call horizon 100% scheduling period is 2 years
after that i done IP10 schedule maintenance plan and save my query if i put call horizon 100% system should create inspection lot same date like 01.01.2010 start date again system should create inspection after 6 months 30.07.2010 but now system show inspection lots 30.07.2010 kindly suggest me if any configure is need
Simplest way is
1.Either shift date to prior six month so that lot will be created 01.01.2010.
or
Initially trigger manually through IP10
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Santhosh
Start date means the date from which scheduling will start, always input your last calibrated date in this field so that you can get the correct calibration dates in the future.
The system is showing correct dates in your case
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.