on 06-02-2010 1:58 PM
dear all
any one explain the integration point of SD and PS
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kindly go through following links for understanding:
-
- [Assembly Process|http://wiki.sdn.sap.com/wiki/pages/viewpage.action?spaceKey=PLM&title=AssemblyProcessinProjectSystems&decorator=printable]
-
-
Thanks & Regards
JP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Santosh,
Can you please explain in detail as I am also interested in knowing the same.
Regards
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The integration between SD and PS is RRB & MILESTONE BILLIN
When you create a Project , you will create the WBS billing element and then assign this to the Sales order
And in the sale B tab will maintain DIP ( or directly assign this to the item categories to determine automatically).
save this order and create the Billing request for the RRB in the DP91
Then normal billing in VF01 for the billing request
ODP1 is the transaction code for DIP profile
ODP11 is used to activate the Biling plan for the DIP profile
Please let me know if you need more details
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
67 | |
14 | |
8 | |
6 | |
5 | |
5 | |
5 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.