Hi experts,

My requirement is to enhance the initial views of cProjects (e.g. Projects, Tasks, Checklist Items, Templates) by an additional tab where I want to provide a custom report. (I know that there is the possibility to add an additional tab for specified project elements, e.g. project definition, project role.)

Is there a way to enhance the startup view of cProjects?

I appreciate any hint!

Thanks in advance!

Regards

Wolfgang

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Kudos

Hi Wolfgang,

The tabs on top level can not be enhanced via customizing. If you would like to add your own tab, the views has to be modified,

dpr_mainframe, vi_tabs.

P.S: the existing tab 'Info' (on the left side of tab Projects) seems to be filled dynamically. may be you can use it for your application.

Kind regards,

Zhenbo

wolfgang_brunneder
Participant
0 Kudos

Hi Zhenbo,

thanks for your answer! First I'll try out the Info tab ...

Regards

Wolfgang

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Wolfgang,

We had similar kind of requirement. We added a new button and a new view using enhancement framework on ABAP webdynpro. It is pretty easy to do.

wolfgang_brunneder
Participant
0 Kudos

Hi Sharad,

thanks for your hint! I'll check it ...

Regards