Hi experts,

Does anyone know if it is possible plan cost in the WBS using ECP by period?

Thanks,

Sara

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Kudos

Hi Sara,

The ECP will not be periodic distributed, as far as I known. The user has to splitt the item into multiple items (for each period) to get this functionality. There is a industrial solution for media, which do the splitt process automatically.

KInd regards,

Zhenbo

Former Member
0 Kudos

IN ECP, period is determined from the start date. If you have several periods, costs are not distributed automatically, but stored in the start date and are changed manually again by calling ECP, if the start date changes.