Hi experts,
Does anyone know if it is possible plan cost in the WBS using ECP by period?
Thanks,
Sara
Hi Sara,
The ECP will not be periodic distributed, as far as I known. The user has to splitt the item into multiple items (for each period) to get this functionality. There is a industrial solution for media, which do the splitt process automatically.
KInd regards,
Zhenbo