Dear experts,
can any one tell me how can I run project scheduling on basis of Work Center Capacity. Is there any specific configuration required for it. In addition to this please guide on process as well.
Thanking in advance.
Regards,
Murtaza
Hi,
Maintain the capacity in work center and assign the work center to
internal activity in the project. Select the caluculation key as
caluculate duration. System automatically caluculates the duration based
on the work center capacities and amount of work entered in Hrs. system
consider this activity duration for scheduling.
For detail information you can refer SAP help.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Network scheduling on projects will be always based on capacity of resources assigned to the activities. Please check SAP Help for network scheduling. Entire process of the scheduling is given in the SAP Help.
Regards,
Mahendra Dighe
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.