on 05-31-2010 11:03 AM
In my Project we are NOT using:
- scheduling of activities
- confirmation of hours on activities
- deliveries on a project
Question: can confirmation of activities be avoided?
Regards,
AHS
If you are not using scheduling and confirmation of activities...then dont use activities at all in your project..just manage with only WBSE's
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Confirmation is a functionality provided in SAP PS to know the exact progress of the project and it is a means by which you post actual cost on the project. As far as your process is concerned Confirmation may not be useful to you. Hence you can follow what Ahmed has suggested.
And if you want to know as to what confirmation does in general you can refer to Ahmed's post or go through SAP Help for detailed info.
Best Regards,
Gokul
Hi,
Ahmed's reply is the most apt one.Hence deleted my previous reply.
Best Regards,
Gokul
Edited by: Gokul on May 31, 2010 3:43 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, you can avoid confirming activities, you have to set confirmation not possible in your control key configuration, then the system will allow you to close the project without confirming them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.