Store Replenishment STO created date and delivery date

Former Member
0 Kudos

Hi

The Store replenishment STO generated out of WRP1 ;

The STO document date and delivery date is defaulted to 3 days later.

ie. WRP1 was run on 31st May. But the delivery date and the STO doc. date is 3rd June.

Is there any way to influence this? We want it to be defaulted to the next date; Replenishment is to be run for th next date.

ie. June 1st.

Regards

2 REPLIES 2

Former Member
0 Kudos

Hello, the delivery date in the STO is taken from the article master, logistics store view, Planned delivery time field (MARC-PLIFZ).

In your case this field has a value of 3 days.

Regads,

Juan Carlos

0 Kudos

Hi Carlos

The master data of the article field MARC-PLIFZ- is maintianed as 0 days.

Basically the replenishment is done in the same day. (DC in the same city as the store)

However still the delivery date in the STO is by default 3 days later.

In the WRP1 screen - the planning date is today date.

Regards