cancel
Showing results for 
Search instead for 
Did you mean: 

Delivery Date Proposal in Sales Order

Former Member
0 Kudos

Hi,

I would get the information about the following

when i enter the Sales Order it Automatically proposes two days ahead of current date.

From where this two days are coming.How can i set this to current date or 5 day ahead

What is the setting for that?

Regards

AK

Edited by: Ajithk on May 29, 2010 12:07 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check the Material Master MRP2, is it maintained for Inhouse production and MRP3 is it maintained Tot. repl. lead time .

Check the in shpping Point(Enterprise Structure->Definition) 1. Load time, 2. Pick/ Pack time

Check whether any route is determined??

with regards

Azeez.Mohd

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Remove tick from proposed delivery date option & leave blank field in lead time days.

Hope this will help u.

Jyotsna.

Former Member
0 Kudos

Hi,

Check the material master. Check the availabilty check and related configuration.Is there any availability check working aorund.

Study the material master completely for the material.

Regards,

Saju.S

Former Member
0 Kudos

Hi,

Pls check "Lead time in days" for order type settings in Tcode VOV8.

Correct it according to yr business requirement.

Reagrds

Sanjay

Former Member
0 Kudos

Dear Sanjay,

Thanks for the prompt reply

I had tested it but it still not coming according to the Lead time in Days.

After i enter the Sales Area it displays two days ahead automatically.

Suppose i want it on current date .I tried to put zero in Lead time in days field in the document type.

Regards

Ak

Former Member
0 Kudos

Hi,

Check the Material Master MRP1,MRP2 is it maintained for Inhouse production if the material is not avaible .

and also check the in shpping Point Back ground, 1. Load time, 2. Pick/ Pack time

Best Regards,

MH