on 05-27-2010 9:22 PM
We are preparing our TDMS set up.
I get an impression from note 1273545 that the highest support package of ECC(HRM) OK with TDMS would be 14 at this moment.
But all of our ECC systems have been applied with SP 15(02/2009)
What we can do in this case?
Thanks a lot!
SP15 of TDMS has not been released yet the latest is SP14
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!
Thanks for your reply.
However, I think that SP14, SP15, etc. are ECC Support Packages, not TDMS SPs.
I went to SMP software download center (quick link swdc) this morning again and verified that for TDMS the highest SP is 5.
Therefore SP14 and SP15 must be the SPs for ECC, not TDMS.
Therefore my question is that since my ECC is already at SP15, how to apply note 1273545?
Thanks!
User | Count |
---|---|
80 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |