Planned Orders shifted to one day ahead in Product availability Overview

Former Member
0 Kudos

Hi Experts

Planned Orders are available on 27.05.2010 for Mat1 and PlantA.

While creating Sales Order when i check check availability , In apo availability overview screen Planned Order is displayed in 28.05.2010.

Simulated requirments on 27.05.2010.

Where as when i check in Product view, Planned Order is available on 27.05.2010.

In ATP simulation also , the same result.

Please advice me.

Regards

Deva

Edited by: vdeva79 on May 27, 2010 3:37 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Experts

Noticed that not only planned orders ,all receipt elements are shifting by one day.

All our plants are maintained in EET time zone.

Now at present we are using Conservative Logic , when i change to progressive then system is showing Receipts one day earliar.

Following settings are maintained in Global settings of GATP:

In ATP Buckets Active of Global settings:

Current = Flagged

Issue Limit: 00:00:00

Shift Receipts: 12:00:00

Local Time= Flaged

Bucket PDay:1

Distr Key:Flagged

Please Help Me.

Reagrds

Vasu

Edited by: vdeva79 on May 28, 2010 7:00 AM

Former Member
0 Kudos

Hi,

You are probably aware that ATP buckets cannot take account of summer time. For this reason, the regulation for local time zones is taken from planning. In this way, the APO system ensures that midnight local time is always on the right date.

If you use totally conservative logic to evaluate the bucket and create sales orders without immediate scheduling, you can acquire a confirmation for the desired availability date by setting the bucket limit later than midnight (local time); therefore, the desired date at midnight still falls in the bucket for the previous day.

If you put the bucket limit later than midnight (local time), the displayed dates of orders, which are still updated in the bucket for the previous day, are in the availability overview before the actual availability date.

I hope this gives some insight.

Regards

Datta

Former Member
0 Kudos

Hi,

Please also check if oss note 1469362 and 798331 are applicable .

Regards

Datta

Former Member
0 Kudos

HI Datta

Thanks for the helpful reply.

We are using SCM 5.0

Current = Flagged

Issue Limit: 00:00:00

Shift Receipts: 12:00:00

Local Time= Flaged

Bucket PDay:1

Distr Key:Flagged

Shall i change any above settings in the system to stop the shift of Receipts and Requiments to Next Day?

Since we are using EET as the Time zones in Calenders in ECC and APO .

My local Time difference with EET is 5 Hrs and with UTC is UTC+8.

Please advice.I searched for the relavant notes but i dont find much informative.

Regards

Vasu

Former Member
0 Kudos

HI Experts

Looking forward for your reply on my ATP Issue.

For any change in Global Settings , i need to reactivate the Live Cache? Please confirm.

Regards

Vasu

Edited by: vdeva79 on May 29, 2010 5:07 AM