on 05-27-2010 2:54 AM
Hi Gurus,
I have deployed once based upon STR's and ATD at Factory. Next week , when i deploy again , where my STR's and ATD quantiy changes, does system replan all Deployment Orders( confirmed STR's) or already deployment orders exist and system try to deploy extra ATD's???
thanks afor your quick reply
Hi Priya,
Whether the deployment orders are replanned or are unchnaged, can be controlled in real time deployment. Under real time deployment, there are 3 options : replan all, replan only unfixed stk transfers and no chnage to the exisitng orders.
i believe if you are looking at the system to respect the existing deployment orders, then you may select 'do not change' option.
you can explore this functionality in /sapapo/snp02 under realtime deployment.
let me know if this helps.
Rgds, Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.