SD BOM - Pricing at component level and delivery at main item level

Former Member
0 Kudos

Can you advice how to setup the follow scenario:

We need to carry out pricing, at component level but in inventory control and WM is only stored the main item,the delivery processing at main item level.

Business scenario:

PP - Process order at main item

Stock entry ( MovT 101) for main item

Consumption (MovT 261) for component level

Sales / Delivery (Mov. Type 601 ) at main item level

Billind at component level ( due to a client request )

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

dear

First,you make that the fieldu201CItem category groupu201Din the MMR of sub-item is LUMF

second,Checking whether the field "pricing "in the sub-item category is ''x'' or not

third,Making that the field " Item rel.f.dlv" is ticked in the main item schedule line category and not ticked in the sub-item schedule line category

Hope that will help you!