Hi All,
I have an issue while creating credit memo. The pricing is incomplete since VPRS value is zero. The VPRS does appear in pricing but the value is zero and there is a RED indicator just before the VPRS condition.
I have checked the material master but the standard price is maintained in the accounting tab.
During pricing analysis , the system shows the following error for VPRS,
" error in qty/value determination",
Diagnosis
This condition has not been determined using condition records. The amount or value should be determined from another data source. For cost (condition category 'G') it is read using conditions from the material valuation segment, for a cash discount condition it is read using conditions from the terms of payment table.
In this transaction an error occurs - the material valuation segment or the terms of payment table could not be read or a currency translation has failed.
System Response
The condition has been provided with the deactivated indicator 'X'
can anyone pls advice as to why this is happening and how this can be corrected.
regards
error in qty/value determination
Go to OMS2, select your material type and execute. There click the boxes for Quantity Updation and Value Updation.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check if the plant is flowing at the item level. Material valuation is at Plant level.
Please check the pricing control / valuation class and price in the material master record- Costing 2 tab.
Please check your pricing procedure if Requirment 4 is assigned to VPRS.
Regards
Sai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Update the cost price of material through MR21 for the particular material and recreate the whole procedure, then you able to receive cost condition
amount.
Hope this helps you.
Regards
Yepuri.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check whether the standard price has been maintained in the material master -accounting view 1. If its not maintained ask your CO consultant to maintain it ( T Code -MR21)and than it will flow in the sales order.
also check the item category whether the determine cost tick is there or not.
hope this will resolve your issue
Regards,
Krishna O
Edited by: Krishna O on May 26, 2010 2:23 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check the Item Category configuration (VOV7) for the field - 'Determine Cost'. It should be activated(checkbox selected).
Regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.