SCM / APO shut down start up; (restore) activities,procedures,best practice

Former Member
0 Kudos

Dear ALL,

What are the generic steps that need to be followed from a Functional Consultant perspective?

I am not sure if this must be part of a Basis thread

Anyone can share & enlighten the forum on this

Some of the steps module wise are

FUNCTIONAL steps

1. DP

1.1 Downloading of CVC's

1.2 Backup of all infocubes / remote query cube

1.3 Download of Planning book data

2. SNP PPDS

2.1 Download Product Master, PPM, Resource data of '000'

2.2 Download 'all order data' from the product overview

TECHNICAL steps

0. Complete off line back up of the system

1. Lock users except admin

2. Stop CIF

3. Stop live cache

What are the restore steps

Anything missed out functionally / technically is welcome

Points would be awarded

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Dutta Saheb & Senthil,

Thanks for the inputs

Other inputs also would be awarded

Regards

Sridhar R

Former Member
0 Kudos

Hi Sridhar,

During shut down & start up of APO system, functional part

involvement is mandatory and it is not an isolated work of

basis alone.

Moreover, in addition to the steps that you have mentioned,

the following are some of the steps that you can follow it up.

1) DP:-

Before shut down:-Copy of data to other simulation versions

from active versions if required. Locking users, Postponing or

rescheduling of jobs accordingly

After shutdown:- Time series consistency checks

Validation of data, Scheduling jobs, unlock users

2) SNP PPDS:-

Before shut down:- Jobs postponement or rescheduling,

Informing users to take the necessary deliveries from stos

from snp for execution

After shutdown:- Download of planning data and validation,

Scheduling of jobs, Order conversions,

3) Technical Steps:- (CIF / Livecache)

Before shutdown:- Rescheduling of integration model jobs

if any,

After shutdown:- Scheduling of integration model jobs,

releasing locked users, Livecache consistency checks,

Delta report, Monitoring and clearing inbound/outbound

queues etc.,

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Sridhar,

Please check SDN Wiki pages in the area of Supply Chain Management. You will find lot useful information about many of the topics below.

Please also check Application Operations Guide for SAP SCM 7.0 and others on the Installation & Upgrade guides in SCM area ( https://websmp202.sap-ag.de/instguides) . These will help on technical operations side.

Hope this helps.

Regards

Datta