on 05-23-2010 6:40 PM
We have many DEV and QA taryget clients in CHaRM.
In the task list, now we have to schedule the import one by one.
Is there any way to schedule multiple target clients together, so that one schedule will be enough for all targets.
I am not talking about scheduling periodic tp jobs which is easy. I am talking about some unplanned tp.
Thanks!
Hi,
Do you have more than one development system in your transport route? If yes, it is not supported by ChaRM. If you have more than one target systems it is possible to perform (schedule) import one by one.
Hope this helps.
Feel free to revert back.
-=-Ragu