PM order by maintenance Plan

Hi,

I have created maintenance plan and task list is assigned to that plan, this task list is assigned to one operation with control key PM03 and i have defined limits for this service.Also the maintenance package is defined as 3 M. In scheduling parameter i have defined call horizon 90% and Scheduling period is 356 days now i have defied start of cycle date is 20.02.2010 and scheduled the plan it shows me 4 line item and first is new start save to call when i save order should be created and PR should be generated but now no order is creation and nothing is there in schedule call tab in IP10.

My requirement is to create order from plan and PR from operation task list.

Help me where i am doing something wrong.Previously i am not giving maintenance package to task list activities.

Edited by: Sukhveer Singh on May 20, 2010 5:18 PM