Hi experts,
I have one question related to capacity , when I create a workcenter and CIF it to APO then why does capacity not cifed to APO.
I can see capacity in integration model only when I edit workcenter as APO resource and select resource type , category etc.
Any inputs will be highly appreciated.
Thanks,
AD
Hi AD,
Under work centre master data in R/3, check whether all the
critical fields for capacity relevant fields like capacity category,
factory calender id, active version, standard available
capacity, capacity utilisation, no of individual capacities,
operating time, capacity, planning details, capacity planner
group, all fields under APO resource tab (under top right hand
side in work centre master data under capacities are
maintained and ciffed.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi AD,
When you CIF a work center at a plant APO doesn't create a work center. It creates a resource for each capacity category you defined in the work center.
Example. If you CIF work center TEST at plant PPL having two capacity categories Machine, Person. APO creates two resources with names WTEST_PPL_001, WTEST_PPL_002. You can chose whether to create Single/Single-Mixed/Multi/Multi-Mixed type of Resources in IMG activity CFC9. By default all resources are CIF'ed as type Single.
So when you use /SAPAPO/RES01 you are not actually looking at work center but you're looking at capacity of the workcenter as a resource.
If you're facing problem in displaying the available resources, check whether you're choosing correct resource type in the Grouping field. You can display Single and Muli activity resouces with their capacities by choosing PPDS type and you can display Single-Mixed Multi-Mixed by choosing SNP.
Hope this helps.
Thanks,
Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do I need to have a separate capacity for each work centre or a capacity can be good for many workcentres?
APO will create the right number of resources with capacities for each workcenter. Number of resources will be equal to workcenter times the capacity categories in it. You need to have a separate resource for each work center and its capacity category.
What is the relationship between capacity and workentre ?
Is it in the scheduling tab of workcentre where we assign capacity? Yes.
Regards,
Mohan