on 05-19-2010 9:59 PM
Hi ALL,
SRM 5.0 SP13 ECS
Service based req with order unit LOT was pushed to SRM . SC got approved in SRM with order unit LOT, PO got approved with order unit LOT and now the PO is in error in process state. I looked up RZ20 to find the message "Order unit PU not covertible into unit Lot of req. We are using material groups and not material masters.
Any idea what is causing this error? order unit seems to be the same, right though the scenario, It was never tried to change at any point of time in the cycle
Krishna
Resolved !!