on 05-19-2010 3:40 PM
In the Sequencing transaction (/SAPAPO/SEQ1), selecting the takt scheduling pushbutton will move all planned orders up to the earliest available capacity. I would like to override the standard system logic, and prevent the system from moving any FIRMED orders forward. Has anybody implemented this sort of restriction?
Hi ,
Please refer to oss note 627377 Consulting note: Model Mix planning and Sequencing.
" MMP and Sequencing do not consider in a special way the input fixed and ATP checked orders. No checks are performed whether an order in input fixed or ATP-checked. MMP and sequencing consider such orders as usual orders in the planning processes."
Model mix planning always uses a strategy with forward infinite scheduling, no matter how you define your resources.
Please also read oss note 769149, Takt scheduling in iPPE line scenario-Restrictions and recommendations
Regards
Datta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.