on 05-19-2010 12:49 PM
Hi,
Capacity Requirement Planning check at the time of MRP: e.g. Optimal loading of work centers / Capacity Planning (Multiple Location/Companies) -Here they have three plants.For example: I have one product produced at three locaton. demand is at A location.Suppose demand is not met by a location A (capacity check) Then it has move location B.If location B has not met capacity to produce then the demand will move to location C.
Please suggest.
Regards,
Sunil Patil
Hi,
PPDS cannot do cross Plant planning.
SNP-CTM will be the best bet, it does consider capacity constraints and can move plan from one Plant to another.
Thanks,
Pavan Verma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I believe it so.
Cost is not the constraint here only capcity is constraint here.
But is it possible to do cross plant capacit planning though pp/ds?
Regards,
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Cross Plant finite capacity planning is certainly possible through SNP optimizer, the costs menthoned in these can be notional, or relative and need not be absolute. Therefore, even if costs may not be relevant in your situation, maintianing these should not be an difficult one. That means while inputting costs, you need to see that the preferred location should have lesser costs.
About PPDS optimization, I thought it did optimization within a plant /location, only .
Regards
Datta
Hi Sunil,
In PPDS Optimiser, if there is shortage in capacity, it tries to place into
the location where capacity is available based on the costs that we
set up in system.
Based on your current scenario, it looks you are looking for finite
kind of planning where capacity is a constraint. In such case, you
can try with Optimiser, which optimises your constraint and
fulfills demand accordingly
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
GS,
I think you are right. PPDS Optimizer does not plan cross-plant, or so I believe. I think the right way would be to plan using SNP optimizer followed by sequence optimization (If required) in PPDS.
Honestly, it depends on the kind of business. A rough cut plan taking into account the bottleneck resources, planned via SNP optimizer, followed by a detailed PPDS plan should do the trick.
Abhi
User | Count |
---|---|
6 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.