I am releasing forecast from DP to SNP for finished product. I had run heuristics to create all dependent requirement for semifished prodcts and as well as for raw material in inactive version.My question is the planned orders are created for finished products, semifinished and for raw materials.
1. I wanted to take only raw materail planned order and move the planned order to active version and release to ECC, can i do that?
Please can any one guide me.
Thanks & regards,
Kumar
Kumar,
I guess you can use the transaction /SAPAPO/VERCOP. Another option is /SAPAPO/VERMER but I have not really seen this working.
Hope this helps.
Abhi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
As Abhi rightly pointed out, /sapapo/vercop is the best
transaction to suit your requirement
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.