on 05-19-2010 8:15 AM
Hi PS gurus>
One question regarding Planning element tick.
In my project in panning profile there is no tick to planning element, either there is no tick in cj20n in WBS overview, then how the system is allowing to plan cost in CJ40 tcode.
Please correct me if iam wrong>>
If planning element is tick then the system will allow to do cost planning in cj40, but if its not tick then the system should not allow to do planning.
In my case the system is allowing to do planning in cj40 inspite of planning element untick.
What will be the reason? Can anybody throw some light in this issue.
Regards,
Ansar
Hi Ansar,
The planning element tick in the planning profile states,
"This indicator controls whether a cost planning is possible only in those WBS elements which were defined as planning elements.
If you do not set this indicator, you can carry out cost planning in any WBS element.
If you check this indicator in the planning profile system will allow you to do planning only for the WBS elements that have the Planning Element indicator ticked.
Even the F1 help for the Planning Element indicator in a WBS element states the same. Do revert if you come across something different.
Best Regards,
Gokul
Edited by: Gokul on May 19, 2010 1:06 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gokul,
Wht does it mean by this statement: If you do not set this indicator, you can carry out cost planning in any WBS element.
My question is in my project planning indicator is untick, then also i can do planning in cj40, as rule it should not allow to do so.
For test case i created new project using another profile, where untick planning indicator, then the system doesnot allow to do planning, it gives error.
It means that something is to do with Profile : project profile or planning profile..Can somebody elaborate this?
Regards,
Ansar
Ansar,
If you indicate planning elements check box in planning profile Txn
OPSB, then system will restrict to do cost planning against the WBSE that indicated as planning element.
If this check box is not indicated in planning profile then system will allow you to do cost planning for all the WBSE irrespective of planning element indicator.
Regards,
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.