on 05-18-2010 8:54 PM
Dear Gurus,
I used network not wbs, so with Time Sheet I assign the hours to network.
Is it possible link cproject task to network ?
If not is there some way to transfer time sheet linked to network in R3 to task linked to WBS element in cProject to confirm the task?
Thank you
Best regards
Vanessa
Hi.
Unfortunately cProjects CATS time reporting with Multi Level Controlling only works with WBS-elements.
Regards / Anders
Ps.
You can link from cProjects to a network activity using objects links. That can in turn be used to add an extra check (validation) stating for instance that the resource need to be staffed in cProjects to be allowed to time report. No MLC CATS though.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
thank you for info.
When you say :
You can link from cProjects to a network activity using objects links.ok
That can in turn be used to add an extra check (validation) stating for instance that the resource need to be staffed in cProjects to be allowed to time report. No MLC CATS though (why?, I should transfer hours put in R3 CATS on network su cProject..)
Thanks in advance.
.
Hi Vanessa,
The problem is the integration, but not the each single point.
You can book the working hours in CATS to a network activity. And even you can link this network activity to a cProject task.
But the features of integrations are still not available, as long as the cProject task (or role depends on scenario) is not assigned (not only linked with object link) to a WBS. That means, the staffed busines partner in cProject does not get the working list, and the confired hours in CATS are not transfered back to cProject.
Kind regards,
Zhenbo
Hi Vanessa,
from technical view it is no problem to do it with a customer report.
After the network activity (ERP) get confirmed. Starting with a cPro task you can get the linked network activity (DPR_OBJLINK),
get the confirmed hours of the activity via a own remote function, get the confirmed hours l in ERP . Transfer the confirmed hours to the cPro task via BAPI_BUS2175_CHANGE.
Kind regards,
Zhenbo
Somebody can help me?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
7 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.