Former Member
0 Kudos

Dear Experts

We have DP and PPDS iplemented in our project.

We have finate planning for 4 weeks.

Forecast is released from DP to PPDS in First 2 weeks demand in Daily level and Remaining 2 weeks as weekly level.

Our Manufacturing cycle time for Finished product is 4 Seconds.

Currently we are using Following Heuristics:

Step1 Heuristic:

Stage Number Algorthm: SAP_PP_020

Step 2:

SAP_REM_002 (Multi Resource Planning)

Assuming today as Monday, when i release DP Forecast to PPDS today, the demand is released in 14 days +2weeks.

When i run PPDS Heuristics , Planned Orders are getting generated on today for all PIRs in the current week.Planned Orders are getting generated even on next monday for all PIRS of Next week.

Offcourse i accept that enough capacity is available for producing.

But in other way the stock levels are raising and Inventory Cost is increasing.

Our Users want Planned orders need to be generated before 24 hours of the Due Date.

How to make my production plan feasable as per our Users Requirments?

What changes need to be done for my existing Production Planning Model? Please give your suggessions.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello KcK,

I guess the issue here is that in weekly buckets all the consolidated demand for the week is being released on the Monday of the week. PP/DS sees this as one consolidated demand and plans. You have to ensure that the demand is split in a given prioportion over the week. You can accomplish this in two ways:

1). Use the BADI /SAPAPO/SDP_RELDATA

2). Use a Daily Buckets Profile/ Period Split profile.

Apologies if I haven't understood the requirement correctly.

Abhi

Former Member
0 Kudos

Hi Abhi

Thanks for your reply.

The demand is not not consolidated on Monday, The demand is available on Tuesday,wed...sunday.We are releasing demand as First 2 weeks broken down to the Daily Level and remaining 2 weeks is consolidated to weekly level.

We are using Time Bucket Profile instead of Period Split profile while releasing the DP Foprecast to the PPDS.

I feel that this issue is not related to DP Demand.

Thanks

Former Member
0 Kudos

Hi Abhishek,

................

When i run PPDS Heuristics , Planned Orders are getting generated on today for all PIRs in the current week.Planned Orders are getting generated even on next monday for all PIRS of Next week.

.............

Do you mean all the planned orders generated on today ( to cover all PIRs in the current week), start on same date and end on the same date ? So you want all these planned orders should have staggered start-end dates, so that just 24 hrs before due date , the planned order starts ?

You are using SAP_REM_002 Heuristics profile and has time buckets profile as Week .

The demand planning is happening correctly here, as you think.

Regards

Datta

Former Member
0 Kudos

Hi Datta

Do you mean all the planned orders generated on today ( to cover all PIRs in the current week), start on same date and end on the same date ? So you want all these planned orders should have staggered start-end dates, so that just 24 hrs before due date , the planned order starts ?

Yes , All the Planned Orders are generated on Monday (Assuming today is monday and releasing the Demand on Today).hus

Example:

DP Forecast for the Current Week for MAT1:

Mon = 10000

Tues= 5000

Wed=10000

Thus=10000

Fri=5000

Sat= 5000

Output in PPDS:

Planned Orders: 45000 on Monday i(From 2 shifts)

(Our Capacity of Production is 50000 Units per Day for Mat1)

So you want all these planned orders should have staggered start-end dates, so that just 24 hrs before due date , the planned order starts ?

Yes we need it before atleast two days before because our manufacturing lead time is 4 Sec for Fin Mat.

You are using SAP_REM_002 Heuristics profile and has time buckets profile as Week .

Yes we are using SAP_REM_002 Heuristics as of now

.Different Time profiles used in PPDS :

Ours is Daily Demnd Plan and Daily Production Plan.(We have 2 shifts and 12 hrs a shift).

Example:

Production Plan on Monday: 2weeks daily(14 DAYS) + 2weeks (Aggregated to weekly level)

Tuesday: 13 days + 2weeks (Aggregated to weekly level)

Wednesday: Current week(5days)14 days2 weeks((Aggregated to weekly level)

total= 19days+weeks(aggregated weekly level)

Thusday:18days+2weeks

Fri: 17 days+2weeks

Sat: 16 Days+ 2weeks

Sunday: 15 days+2 weeks

Demand Plan:

In DP, forecast is created in Mixed Buckets:

3Weeks in Days + 49 weeks in Weekly Level

In Demand Planning while releasing the Demand to PPDS:

On Monday: 14days+2 weeks(aggregated)

On Tuesday: 13 Days+2 weeks

Wed: 19 days+2weeks

so on.. till sunday.

Awaiting for your reply..

Thanks

Edited by: kck.0623 on May 18, 2010 5:15 PM

Edited by: kck.0623 on May 18, 2010 5:19 PM

Edited by: kck.0623 on May 18, 2010 5:23 PM

Edited by: kck.0623 on May 18, 2010 5:36 PM

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

Will you please check strategy profile for following ?

Strategy profile:

Strategy: should be Backword with reverse

Cross-strategy parameters

Desired date: Current, Earliest date, Specified date, u2026 setting should be Specified date

Regards

Datta

Former Member
0 Kudos

Hi Datta

Sorry for the late.

I tried with all options available in Strategy profile but same result.

As we have sufficient capacity, system is creating planned orders for the day1 of the week.

Manufacturing time of Finished Product is 3.5 Secs.

Any other solution for my requirement?

Regards

Edited by: kck.0623 on May 25, 2010 5:03 PM

Answers (3)

Answers (3)

Former Member
0 Kudos

the problem here is.......Products are produced with 4 weeks shelf life, yet stock becomes unsalable with less then 1 week remaining shelf life. This means, production in week 1 can supply sales during week 1 to week 3, but canu2019t supply sales in week 4.

Former Member
0 Kudos

NRG-A NRG-B NRG-C NRG-D NRG-E are the finished goods

Former Member
0 Kudos

hai guyz...

can anyone suggest me on the below problem..sales forecast for finished products, with below quantities

Sales Forecast In CS XXF100 XXF110 XXF120 XXF130 XXF140

Week No. Week Commencing NRG-A NRG-B NRG-C NRG-D NRG-E

Week 27 2010 28/06/2010 236 132 385 76

Week 28 2010 5/07/2010 184 103 300 59

Week 29 2010 12/07/2010 220 123 359 70

Week 30 2010 19/07/2010 182 102 297 58

Week 31 2010 26/07/2010 199 111 324 64 500

Week 32 2010 2/08/2010 125 70 204 40 300

Week 33 2010 9/08/2010 176 99 287 56

Week 34 2010 16/08/2010 203 114 331 65

Week 35 2010 23/08/2010 234 131 381 75

Week 36 2010 30/08/2010 186 104 303 60 300

Week 37 2010 6/09/2010 245 137 399 78

Week 38 2010 13/09/2010 164 92 267 52

i want out a feasible production plan, which can satisfy Sales volume without causing any stock losses

Production plan:

Production Volume in CS XXF100 XXF110 XXF120 XXF130 XXF140

Week No. Week Commencing NRG-A NRG-B NRG-C NRG-D NRG-E

Week 27 2010 28/06/2010

Week 28 2010 5/07/2010

Week 29 2010 12/07/2010

Week 30 2010 19/07/2010

Week 31 2010 26/07/2010

Week 32 2010 2/08/2010

Week 33 2010 9/08/2010

Week 34 2010 16/08/2010

Week 35 2010 23/08/2010

Week 36 2010 30/08/2010

Week 37 2010 6/09/2010

Week 38 2010 13/09/2010

we may use whatever method to level load production,....please suggest me guyz...

thanks