BDC for Inspection plan

Former Member
0 Kudos

Dear QM Gurus,

I have recorded BDC for QP01.

At the time of recording system was not asking for "Inspection Method". Also we have not created inspection method for any material. But after completion of recording, abaper has done his job to run that BDC.

Now when i am uploading template after entering MIC, system popup mandatory screen to enter inspection method. Here we stuck.

Please guide.

Thanks in advance.

Kailash Thakkar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks.

vineeth_varghese
Active Participant
0 Kudos

Check whether you entered plant number mistakenly, this may some time prompt for inspection method data. If so remove plant.

Thanks

Vineeth

Former Member
0 Kudos

Hi Kailash,

Inspection method is not mandatory field, you should be allowed to save the Quality plan w/o entering method. Please check following :

1) Just check you have not assigned any method while creating MIC.

2) Ask ABAPER to modify the program to exclude the inspection method from BDC.

3) I problem not resolved by any other way, then create a simple insp method like visual check and assign it to all MIC's in Quality plan.