on 05-14-2010 1:45 PM
Hi Experts,
Please help
Inspection closure not meaningful due to delivery certificate status
Message no. QV137
Diagnosis
You want to make a usage decision for an inspection lot with partial lots. This is not logical considering the status of the delivery note.
The batch split in the delivery note is still incomplete.
Procedure
Make the usage decision at a later time.
Basically the delivery is processed to a state that the inspection lot can be processed. What kind of inspection lot origin does this have. Do similar products have the same problem.?