Hi All

We have maintained two different factory calendars at shipping point and route , These 2 calendars are having different working days .

Now at the time of calculating dates in sales order , which calendar system will consider for the below fields

Goods issue date

Loading date

Material avail.date

Transportation Plan.

Is it from Route calendar or shipping point calendar the system consider the working days. Please let me know which calendar got exact influence on what filed.

Regards

Sri

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

This will be the shipping point calendar.

Former Member
0 Kudos

HI all

what i found is

The factory calendar which we assign at routes will influnce the dates in sales order. The time's ( Transit time , transportation lead time ) mainatined with route, will get influenced with the calender assigend to the route . Table (TVRO) .

If factotry calendar is not mainatained int he route , then shipping point calendar will be considered

If both are mainatined and they are different , the route calender will influnce on the times/ days mainatined in config(TVRO) remaning dates will be influenced by shipping point calendar

Requested delivery date is influnced by customer calendar

Regards