Hi All
We have maintained two different factory calendars at shipping point and route , These 2 calendars are having different working days .
Now at the time of calculating dates in sales order , which calendar system will consider for the below fields
Goods issue date
Loading date
Material avail.date
Transportation Plan.
Is it from Route calendar or shipping point calendar the system consider the working days. Please let me know which calendar got exact influence on what filed.
Regards
Sri
ans
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi it will take shipping factory calender into consideration !!!
Also u can define the customer calender ( Public, Holiday,Fatory ) and good recivening hour in IMG under Sales & DIst -master dat-BP-shipping.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krishna
what i found is
The factory calendar which we assign at routes will influnce the dates in sales order. The time's ( Transit time , transportation lead time ) mainatined with route, will get influenced with the calender assigend to the route . Table (TVRO) .
If factotry calendar is not mainatained int he route , then shipping point calendar will be considered
If both are mainatined and they are different , the route calender will influnce on the times/ days mainatined in config(TVRO) remaning dates will be influenced by shipping point calendar
Requested delivery date is influnced by customer calendar