on 05-13-2010 8:09 PM
Dear all:
We need to try some basics functionalities of charm for demo purpose in our system. While creating the project, we have to u201CActivate Change Request Managementu201D, will it affect the TMS in the system? (as far as I know, CHaRM takes over the TMS). Is there any way to play around with CHaRM without interfering with the daily basis activities in the target system?
Thank you very much!
Hi Federico,
In the Project
System Landscap ->Change Request tab
goto Project status switches and make it yes
this will hep you to use the request in satellite system using STMS as usual
normally we set it to No option so that it will happen via CHARMS and not with Satellite STMS .
Hope ans ur query
Regards
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you prakhar!
What do you mean by "goto Project status switches and make it yes", are you meaning the switch "Activate change request management"? If so, switching it off wouldnt let me create a Task list to test other charm functionalities?
Hope Im being clear with my question
Thank you very much again,
Federico.
Hi Federico,
The Project Status switches is in the IMG project, Go to your IMG project tab, and click on the IMG project and hit display, it will take you to the IMG project in ur satellite system. then go to transport requests tab. There you will be able to see the CTS project status switch.
Regards,
Sneha Vyas.
User | Count |
---|---|
83 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.