Report for resources against projects

Former Member
0 Kudos

Hi,

I'm looking for a PS report that can list available / utilized resources against projects. Is there a standard report available for this requirement in SAP?

Regards,

Aman

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

CMP2, CMP9 T codes you can use for the same.

With Regards

Nitin P.

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi Aman!

Take a look at these 2 reports: CN50N (Project Info System: Capacity Reqmts Initial Screen) and CMP9 (Workforce Planning - Reporting).

In CMP9, you can view the workforce planning in 3 different views: project, work center and personnel resource.

I think this might help you.

If you need any other help, tell us!

Best regards,