Hai gurus

Could u provide the scenarios with example the period control works in rate steps

Period Control 01 - month based using key date

period control 02 - month based with intervals

period control 00- to the day

Also to be note

if we use period control 02 ,Is it possible to include Dynamic period control variant in the rate steps .

Kindly suggest Ur comments on the same.

sam satheesh

1 REPLY 1

former_member442034
Active Participant
0 Kudos

Hi,

The period control in the rate steps is used for the billing of the time depended fees.

00 - To the day

You have billing period from 15.01.2010 till 31.03.2010

- the whole billing period is billed to the date - 31 days

01 - Month based using key date (TE422-STICHTAG)

Is used for monthly analyses of a period.

A period contains a certain number of months. In the process, the key date determines whether a month is included in the respective period or not.

Example

The key date is the 15th of the month. As a result, in a monthly analysis, the period

January 3 - December 22 covers 12 months

January 16 - December 14 only covers 10 months