cancel
Showing results for 
Search instead for 
Did you mean: 

Product master

Former Member
0 Kudos

If change the material in R/3 with MRP Profile , then is it possible that the changes will reflect in APO?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Viajysinh,

If the MRP view some fields get changed, then this will trigger a change pointer and the APO product master will get updated.

Regards

Datta

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Patil,

If u have changed APO product master related fields in ECC Material master definatly these changes will appear in APO Product master immeadiatly, if the settings in CFC9 in ECC the change transfer for materail master is 2. If it is 1, then changes will write in the change transfer pointers.

You have to transfer these material master changes Using CFP1 or by regenarating and reactivating Integration model using CFM1 and CFM2.

Then your changes will be transferred to APO

Sree

Former Member
0 Kudos

Hi Patil,

If a valid active integration model exists between R/3 and APO, the

changes can be transferred to APO

Regards

R. Senthil Mareeswaran.