on 05-12-2010 10:10 AM
in my production clinet i done this senario we done golive 5th april till date we are working back date posting like po migo and sales order and production orders during some date problem now my query is 02.04.2010 posting is done one finished material so that material is availble in unrestricted when i delivery that material system not pickup so i think that that material not posting to same date the system is pickup current date so i reversal that material when i post same quanity to back date posting system show error Deficit of BA St. in QI prev. 300 EA : M01RZ02005 1100 FG01 01D10A039 M7 21
kindly give to me suggetion what i can do
Hi ,
In MMBE go to that lot (mean quantity) and check environment >> material movements check the posting date for that quantity.
If the lot is posted / or stock is loaded on 5th April system may not accept stock posting on 2nd April. So please check the posting date for that quanity and accordingly post the stock on that date.
Best Regards,
Shekhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
not working
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In stock posting screen there is one field "Document: ( Hat like symbol) ,here change the stock posting date.
Explore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.