on 05-12-2010 4:50 AM
Hi Guys,
I just wanted to ask how can I maintain Proof of Delivery in R/3 I have a PO Number and Delivery Number as input.
Thanks.
Chris
Hi Chris,
Prof of Delivery(POD) can be Maintained at Customer Master level
We can maintain at Customer maste Level T-code XD01
Then Follow up by T-code VLPOD>Change Single Document
Or
VLPODQ->Automatic POD confirmation
Regards,
Seegal