Hello all,

I am doing a local client refresh and security was backedup in target client using SCC8 (export) for later import. It created three transport request for sap_user profile while doing export - <SID>KO, <SID>KT, <SID>KX.. I understand that I need to go to STMS for import. Can anyone tell me if I need to import all 3 transports or just KT? Is there a reccommended wait time after these transport before executing SCC7?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear DK,

You have to include all the 3 TRs into your import queue and import all the 3.., once they are imported successfully thats when you have to run your tx-code: SCC7 for post-processing.

Just ensure you have no users logged in and no active background jobs by the users. This is just to ensure data integrity.