on 05-11-2010 11:16 PM
Hi,
We are having 2 Landscapes,
DV1 (100) --> QA1(100) --> PR1(100)
DV1 (200)--> QA1(200) --> PR1(100)
Both these landscapes are added in the ChaRM Project landscape. When we have created a correction and created a Workbench request, we were getting the option to choose the DEV system and we chose DV1(200). When we tried to create a TR for Customizing in DV1(100) it did not provide the pop up for DEV systems and directly created the customizing request also in DV1(200). We were unable to even create the TR in DV1 (100) - using the task 'Create Transport request' in the Task plan for the corretcion (It gave an Error that the DV1(200) is the Development system for this change).
is this the standard behaviour? can't we have TRs from different client/ development systems under the same correction?
Please clarify?
Regards,
Kathir
Hi Karthik
Which version of Solman are you using
Secondly the option comes only in case of Normal corr and not in Urg corr
this is a standard behaviour in urg corr and not in the case of normal corr
Hope it helps
Regards
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
As i said earlier you will get option to choose system for creating Transport Request only in case of normal corr
but in case of urg corr
you need to give ibase for production of the cocerned landscape
e.g if u have ecc and bi and want to create transport in ecc then giv ibase for prd of ecc only
because you will not get pop up in urg corr
Hop doubt clarified
Regards
prakhar
Edited by: Prakhar Saxena on May 12, 2010 6:17 AM
User | Count |
---|---|
88 | |
10 | |
10 | |
9 | |
6 | |
6 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.