on 05-11-2010 6:51 PM
Hi,
Question on setting and then reversing TECO status for a WBS element.
When a project is closed technically in project builder, all underlaying items (wbs, network/activity) are technically closed as well.
When you try to undo this, only the status of the top element is changed, not the underlaying items.
Is there any way in which we get the underlaying items changed as well (mass change is not an option)
Regards,
Jatinder Bansal
You can try two methods :-
1. Open project in project builder, Select project definition and then go to WBS Overview under project definition, now select all WBS Element and then undo TECO status. Now all the WBS status will be updated. But, this will not have any effect on network and its activities.
2. Open the project in planning board, now select all the objects, now undo the TECO status. This will change the status of all selected objects like WBS,Network and activites....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can revoke the lower WBSE status by using functinal module
BAPI_BUS2054_GET_STATUS.Discuss with your abaper to excute the same.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jatinder
No, you have to do it one by one
BR/Håkan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.