on 05-11-2010 5:45 PM
Hi All!
How can i have the today date in "Requirement Date for the Component" and "Manual requirement date" by default when create/insert a new material component in CJ20N or CN21/CN22.
Thanks
Regards,
Adelino Pereira
Hi,
If you manually overwrite the requirement date that has been determined
automatically, Manual Requmt date indicator will be set automatically once you
press enter. So Make the requiremnet date as mandaotry field.
In SPRO network profile remove the indicator for Align fin date.
I think there is no option in the standard to make default the "Manual
Requirement date" in CJ20n
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!
but what i want is the network activity component requirement date default to current date.
I have seen the Note 1127691 - User exits while processing materials in Project Systems; but i didn't find any to use the current date.
There are a post about this:
Link: [Network activity component requirement date default to current date |]
Thanks
Regards,
Adelino Pereira