Today date in Requirement Date for Component and Manual requirement date

adelino_pereira
Explorer
0 Kudos

Hi All!

How can i have the today date in "Requirement Date for the Component" and "Manual requirement date" by default when create/insert a new material component in CJ20N or CN21/CN22.

Thanks

Regards,

Adelino Pereira

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

Hi,

If you manually overwrite the requirement date that has been determined

automatically, Manual Requmt date indicator will be set automatically once you

press enter. So Make the requiremnet date as mandaotry field.

In SPRO network profile remove the indicator for Align fin date.

I think there is no option in the standard to make default the "Manual

Requirement date" in CJ20n

Regards,

adelino_pereira
Explorer
0 Kudos

Hi!

but what i want is the network activity component requirement date default to current date.

I have seen the Note 1127691 - User exits while processing materials in Project Systems; but i didn't find any to use the current date.

There are a post about this:

Link: [Network activity component requirement date default to current date |]

Thanks

Regards,

Adelino Pereira

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

We have similar requirement to default the option for manual requirement date. So far we had no luck with user exits or Badis.

Have you or anyone had any luck meeting this requirement?

Thanks,

Former Member
0 Kudos

You can try out with screen variant,if all the users require this manual requirement option.