Hello All,
Is to possible to use the Fair Share rule B with Interchangeability in SNP Deployment (SCM 7.0)???
Thanks,
Siva.
Hi Sivaprakash,
A short answer to your question is NO.
The deployment heuristic and the deployment optimizer take into account SNP product substitution orders that were created during heuristic-based or optimization-based planning in Supply Network Planning (SNP).
The fair share rule A (Proportional Distribution Based on Demands) or one of the push rules, Pull, Pull/Push, or Push by Demands as the distribution rules for the deployment heuristic in the product master data is respected . The other distribution rules are not supported.
Therefore the Fair Share Rule B: Proportional Distribution Based on Target Stock will NOT be respected with product substitution.
Please find additonal document help on following URL:
http://help.sap.com/saphelp_scm70/helpdata/en/1c/4d7a375f0dbc7fe10000009b38f8cf/frameset.htm
Please also refer to OSS note 1405636 SCM 7.0 Implementation recommendations SNPCTMVMI.
I hope this gives you insight.
Please confirm.
Regards
Datta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.