cancel
Showing results for 
Search instead for 
Did you mean: 

Bacground Forecast Run - Error - data that is currently locked

Former Member
0 Kudos

Dear All,

I am scheduling the Forecasting Job in Background on daily basis , sometime in logs i get the below ERROR...

" Selection accesses data is currently locked"

Can any body help me...

what are the possible reasons? i mean except the User is working in the planning book?

Suppose if the only reason (User is in the planning book) then how can we avoid this error??

Is there any way , if the user is in the planning book .then also we can avoid this error!

Plz help

Regards,

Rajesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rajesh,

Check the lock using transaction sm12

You can control the users by locking/unlocking during forecast run

using transaction su10

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Rajesh,

In additon to recommendations from Senthil as above, please also check if in system there are other background jobs e.g. forecast processing , macro calculations etc. with the same selections.

Some times there are more than one job running for some time in parallel, in DP with probable same selections.

Regards

Datta

Answers (0)