on 05-11-2010 5:39 AM
Dear Experts ,
I have a question regarding General task list assignment in Plant Maintenance
i need assign General task list in Equipment , i dont want to create Equipment task list
for each and every Equipment
Please throw some ideas , i checked in Equipment for any field to assign general task list bt i cannot able to find
Thanks in Advance
Regards
Raj
Hi Raj,
You can create a PM plan for the equipment and then assign General task list to that plan. It works great and is a time saver.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello Raj.
you can check all the task list for equipment via Enviroment -> task list, but the assgined TL are equipment TL. unfortunately, no option in equipment master data to assign general task list.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.