Hello Experts,
In my project, planning is done using activities, so ideally CN41 report displays the plan values (Proj.cost sched.000) for the network and the WBS assigned to the netwok is same.
E.g. 1000 USD planned for network = 1000 USD planned for the WBSe.
But for one of the project, I see the WBS planned value is more than that of Network though we plan only in NTW.
I can see a sales order assiged to this WBSe for which sales order billing value 1500 USD displayed in CN41 in revenue plan column.
Is there anything like sales order planning? the billing value is for revenue generation but does sales order planning also required? like to complete the sales order, how much is my plan cost? does the sales order plan cost gets updated in the WBS plan cost?
I am asking this question becasue if i look in CJ41 (Display WBS planning) I can see all the cost displayed in the column Order/network
Please clarify me on the sales order assignment.
Regards,
Hi,
In Sales order also ,you can see the Cost and price,all depends upon the Pricing procedure conditions like PR00 etc.....
Whenever you linking the sales order with the WBSE,You can see the Planned Revenues that you have maintained in the Sales order.
The planned cost is either from your Network Activities like Materials,Servies,Labor etc or planned cost through CJ40/CJR2/ECP/Unit Costing etc.Network is an order type of Cat 20 .
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the reply and clearing my doubt on sales order.
my problem is as below:
Cost planned on the network: 1000 USD
as in my project, planning is done only on NTW, CN41 report should show:
Project Object---- Proj.cost sched.000
WBS.0001------ 1000 USD
Network --- 1000 USD
however, CN41 report is showing as below:
Project Object---- Proj.cost sched.000
WBS.0001------ 1100 USD
Network --- 1000 USD
I can see that the 100 USD are directly planned on the WBSe if I see the values as non aggregated but I am not able to understand how 100 USD are planned on the WBSe.
If I see CJ41, I can see Planned 1100 USD under the column Order/network
This means that all 1100 usd's are planned using orders/network.
Please help me understanding why there is a difference of 100 USd's at network and WBS level and how to find out where the additional 100 USDs are planned on WBSe.
Thanks
Run this report S_ALR_87013532 - Plan/Actual/Variance in , Select the WBS Element in question and double click 'business transaction" under navigation...you will see the breakdown of cost according to business transaction, now you can find which business transaction caused that extra 100USD.