on 05-07-2010 10:50 AM
Dear Experts,
The scenario is that we use network activity for posting the cost on project. When I run settlement on WBS Element, system performs the following steps
1. Network = Credit - TO - WBS = Debit
2. WBS = Credit - TO - AUC = Debit
BUT system posts an additional debit entry with same amount on WBS Element, due to which WBS Element shows the double cost in financial reports. Joint Venture Accounting is activated with IS Oil.
Please guide if I have missed something in configuration or advise any other solution. Thanks.
Regards
Murtaza
Edited by: gmurtaza on May 7, 2010 11:51 AM
Hi,
It happends typically in case of capital projects, in which cost gets settled to AuC. When cost is settled to AuC, it credits the expenses w.r.t. WBS element and debits the AuC, which is again assigned to WBS element and we end up is seeing double cost in Financial Reports after AuC settlement.
To avoid this problem, please define a valuation category, in which all AuC accounts (cost elements) are maintained and suppress this value category. This will help in elimnating this debit entry w.r.t. AuC reflecting in the report.
Refer the SAP Notes: 51971 and 676123
Trust this helps.
Regards,
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check your settlement rule for the WBS Element..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check in the path, IMG - Financial Accounting(New) - Asset Accounting - Integration with general ledger - Additional account assignment objects - specify account assignment types for account assignment objects
Check if in the above path for Generic company code 0001 , Depreciation area 01 , if the transaction type 116(Acquisition - internal settlement to AuC) has been ticked as account assignment object.
T-code - ACSET
If yes, then this setting is mainly made for reporting purposes to show the costs, but when you do the asset settlement, this AUC amount will get normalised.
During the period of AUC & Asset settlement, these amounts will be shown in the reports; but will not consume your actual budget.
Hope the above is useful.
Regards,
Deepa
Edited by: deepa rani on May 10, 2010 5:42 AM
User | Count |
---|---|
69 | |
14 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.