Hi Experts,
I want to do the cost planing at activity level so for this i have create one sub activity with selecting of control key PS03 which having select indicator Gen. Cost ACt. to allowed to doing cost planning. But I am doing confirmation on main activity level hense when i have seen the report in CNE5 result get display like Cost planning i can see at Subactivity level & confirm progress i can see at main activity level.
So is it possible to do it at main activity level. (Cost planning & Progress Confirmation)
Best Regards,
Vishal
I think you want to update the progress and actual cost of sub-activity to main activity like a parent child relationship between the sub-activity and main activity.
It is not possible to update the progress and the cost of sub-activity to main activity be cuase it is not parent-child relationship between those. This is the one requirement coming from many customers even where I have worked, unfortunately it is not sub-activity of main activity but activity element.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I dont understand your question fully, please give some more details
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.