Statistical WBS setting.

Former Member
0 Kudos

Dear All,

We have a WBS which is account assigned and have also some actual postings on It,the project is defined as statistical(tick set at project definition),as we can undo the statistical tick at the WBS level(control tab), the WBS does not have the statistical tick marked, and actual postings have been done.now the statistical tick/CCtr post is greyed out.

Is it posible to have the statistical tick reset and set the costcenter.ie to set the WBS as statistical again,

,i tried and reversed the actual, the fields are still greyed out..Is there any solution for the same

Request all to please let us know your recommendations on the scenario above.

Thanks and Regards,

Vinayak.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

As an alternative solution, you can create new WBS Element with statistical indicator checked, and then settle the cost of old WBSE to the new WBSE and after that close the old WBS Element.

Former Member
0 Kudos

Hello Ahmed,

Thanks for your reply..We have our settlement profile set as not for settlement.

Any other alternative please all are welcome.

Thanks and Reagrds,

Vinayak.

former_member203098
Active Contributor
0 Kudos

Hi,

As told by Ahmed, you have to create new statistical WBSE and run the Txn KB15N manual

cost allocation. Enter the old WBSE and new WBSE with cost element and

amount. Old WBSE will be credited and new WBSE will be debited.

I hope it will work in your case.