I need advice on the difference between different 'Adopt putaway qty'.
Blank - Control through movement type
1 - Stock placement qty adopted into delivery as delivery qty
2 - Copy stock plcmt qty as deliv. qty into delivery and post GI
3 - Stock placement qty not copied into delivery as deliv. qty
4 - Do not take putaway qty as delivery qty, but post GR
What the significant difference, and impact among them?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1 - Stock placement qty adopted into delivery as delivery qty
If the inbound delivery has 10 qty of item A. The transfer order created from inbound delivery has 10 qty. But you confirm only 5 qty in the putaway TO, the inbound delivery qty will be updated to 5 qty.
2 - Copy stock plcmt qty as deliv. qty into delivery and post GI
If the inbound delivery has 10 qty of item A. The transfer order created from inbound delivery has 10 qty. But you confirm only 5 qty in the putaway TO, the inbound delivery qty will be updated to 5 qty and the GR will be posted
3 - Stock placement qty not copied into delivery as deliv. qty
The stock placement qty is not copied to the inbound delivery and partial goods movement of the inbound delivery could be manually done.
4 - Do not take putaway qty as delivery qty, but post GR
The stock placement qty is not copied to the inbound delivery but the partial GR is automatically done.
Hope this helps.
Thanks
Swagat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.