Hi All,

For some reason history is not always captured for all events on CN60.

When I confirm an activity I put on the Actual date, reflecting on a milestone. However when I go to CN60 to do an audit check, sometimes the new value column does not reflect latest changes.

Please help

Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

Are you looking for activities or milestones?

Former Member
0 Kudos

milestone

former_member203108
Active Contributor
0 Kudos

If you have problems in change documents for milestones then please check these notes, it may help you

Note 1001865 - No change documents created when WBS Milestone is changed.