on 05-04-2010 4:38 PM
Hi,
I am trying to find a way to automatically generate clean-out orders in a certain resource. The restriction I have is that after 7 times I use that specific resource I have to clean it.
Is there a way to insert the cleaning order or some other down-time so I can plan the cleaning?
I am considering the use of production campaign planning as an option to program those cleaning orders.
thank you in advance
Fernando
Edited by: fmorenoo on May 4, 2010 5:43 PM
Hi Fernando,
1) In /sapapo/res01 transaction, based on the lead time of products for
7 days that the resource is going to get scheduled, you can block in
advance before the planning run happens (at the downtimes tab) and
then carry out planning run. This will avoid the resource not getting
scheduled during the period.
2) Try the badi /SAPAPO/CRESDOWNTIME
3) Try the sap note 448601
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Senthil thanks for your quick response,
The issue I am dealing with is that I don't know when I will have the downtime because my production orders don't have the same duration so if I schedule a downtime using /sapapo/res01 I will probably shorten the capacity of my resource. On the other way, if I cannot use the badi /SAPAPO/CRESDOWNTIME because once I start using my resource I cannot stop it.
So what I am thing is about getting a Heuristic or a certain optimization process where I can first plan my production orders and then insert the downtime where it corresponds after 7 times of using my resource.
Thank you,
Fernando
Edited by: fmorenoo on May 7, 2010 11:56 PM