Hello Friends
I created the project and allocated the budget in 2009,
I created PR in Feb 2010, but the problem is while i am changing the quantities in ME52N.
I am getting the error message :item XXX WBS element budget exceeded
Even i carry forwarded the budget from 2009(CJC0) to 2010.still the same problem exists.
Regards
Kiran
Hi,
Check the delivery date in the PR. If the delivery date is for next year
2011 system displays the error message.
If problem still persists then reply the thread with error message number.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Good day,
I have the same problem. I am not working against a specific WBS element and there is budget in the cost center and GL account, and the release strategies are correctly maintained, but upon creation the PR, I still get the error budget exceeded.
I am desperate for assistance please. Is there maybe somewhere else where budget can be checked, except on KP06, which is maintained.untitled.jpg
Anita
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.