on 05-03-2010 6:47 PM
Hi,
I need to make a client copy from the BI Productive System to the BI Development System.
I did already one with the transaction code scc9 and use the profile SAP_ALL, and unfortunately it didn´t copy all.
Should i use an export and then a import? homogeneous/heterogeneous system copy or i can do another this procedure with another profile?
Kind regards.
Nuno Silva
Hi,
As per the SAP best practice, its not recommended to do a client copy or client import/export between BI systems. Only recommended process is system copy.
Thanks & Regards,
Sharath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Use System Copy.
Also check [SAP Note 886102 - System Landscape Copy for SAP NetWeaver BW|https://websmp230.sap-ag.de/sap%28bD1lbiZjPTAwMQ==%29/bc/bsp/spn/sapnotes/index2.htm?numm=886102]
Hope this helps.
Thanks,
Naveed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.