Hi,

I need to make a client copy from the BI Productive System to the BI Development System.

I did already one with the transaction code scc9 and use the profile SAP_ALL, and unfortunately it didn´t copy all.

Should i use an export and then a import? homogeneous/heterogeneous system copy or i can do another this procedure with another profile?

Kind regards.

Nuno Silva

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As per the SAP best practice, its not recommended to do a client copy or client import/export between BI systems. Only recommended process is system copy.

Thanks & Regards,

Sharath

Former Member
0 Kudos

Use System Copy.

Also check [SAP Note 886102 - System Landscape Copy for SAP NetWeaver BW|https://websmp230.sap-ag.de/sap%28bD1lbiZjPTAwMQ==%29/bc/bsp/spn/sapnotes/index2.htm?numm=886102]

Hope this helps.

Thanks,